PRODUCTION MANAGEMENT (2009)
Time : Three Hours ] [Maximum Marks:70
Note: All question have to be attempted.
Section-A
1. A product has to undergo with three different operations to
be performed at three machines, named M1,M2,M3 in a
manufacturing company.The standard operating time per
machine with respective operator's efficiency is as follow :
Standard hours per
Operator's
Machine component/product efficiency
________________________________________________________
M1 0.16 80%
M2 0.23 100%
M3 0.09 90%
information given :
(i) Manufacturing unit of a company operates on six days in
a week.
(ii) manufacturing unit operates two shift of 8 hours every
day.
(iii) machines are available for both the shift on six working
days in a week.
(iv) There is no sequence of operations.
Calculate how many of the machines of M1,M2 and M3
shall be required to produce 4800 components or products
per week ?
Section-B
2. Write short notes on any four of the following
(upto 50 words) :
(a) Preventive vs Breakdown maintenance
(b) Technical obsolescence
(c) Productivity
(d) R and D Deptt.
(e) Value engineering
(f) L. I. F. O.
(g) Product diversification
(h) Opportunity
3. What do you understand by the term 'Production' ? Discuss
the responsibilities of a production manager.
Or
What is the importance of Economic Order Quantity
(E. O. Q.) ? Show its calculation and applications in
production planning and control.
4. What is product mix determination ? What are the major
factors effecting product mix decision in a large manuf-
acturing concern ?
Or
"No inventory is the best inventory." Illucidate the
statement.
5. Define different attributes determining quality of a
product. Explain SQC as a technique of quality control.
Or
What are the distinct stages of product development ?
Highlight key areas to be taken into consideration during
product development.